The Lingao project.

Phase 150,000 t/yr gross
Net removal~43,000 t/yr
SiteJinpaigang, Lingao

Phase 1: 50,000 t/yr gross, ~43,000 t/yr net. Delivery subject to permits and MRV registration.

Planned investmentRMB 460 million
Site~94-mu industrial plot in Jinpaigang (recommended, March 2026)
ConstructionSubject to approvals
StorageCNPC Southern Oilfield (MOU in progress)
Captura's Kona pilot plant, Hawaiʻi

Captura's 1,000 t/yr pilot at Kona, Hawaiʻi, in operation since February 2025. Image: Captura.

Carbonjour team at Captura's Hawaiʻi pilot plant
Keāhole Point, March 2025. Site visit by the Carbonjour team. Photos: Carbonjour.
Pre-treatment area at the Hawaiʻi pilot
Pre-treatment and intake area.
Pilot plant equipment at Keāhole Point
Pilot plant, Keāhole Point.

Delivery control.

What we control, what we depend on, and what we do not.

We control

Engineering and delivery

  • Plant design under the Captura agreements (FEL-1)
  • Construction management and commissioning
  • MRV design, monitoring and data collection
  • Offtake contracting and delivery scheduling
We depend on

Permits and partners

  • EIA, sea-use approval and land allocation
  • CO₂ storage agreement with CNPC Southern Oilfield
  • Power purchase agreement with CHN Energy
  • Grid connection
  • Captura's FEL-1 deliverables
Outside our control

Policy and market

  • Permitting and approval timelines
  • Carbon market and registry rules
  • International buyer demand
  • Weather and construction conditions

Where things stand.

Signed
  • Captura – China MOU (August 2024)
  • Captura services agreement and SOW-001 (November 2024)
  • CHN Energy (Hainan) power MOU, non-binding (April 2026)
Issued
  • Lingao site-intent letter (March 2026)
Accepted
  • Park admission application (March 2026)
In discussion
  • CO₂ storage MOU with CNPC Southern Oilfield
  • Further agreements with Captura
Planned
  • Construction, commissioning and expansion

Why this site works for DOC.

86cm/s
Maximum surface current (design threshold ≥50 cm/s)
1.8m
Mean tidal range
0.2–0.6m
Significant wave height
50–100m
Intake distance offshore, water depth 3–5 m

Source: Jinpaigang master plan (2020–2035), as cited in project documents.

What has happened, and what comes next.

Aug 2024
Captura MOU

China MOU signed, covering FEL-1.

Nov 2024
Services agreement

FEL-1 scope and SOW-001 signed.

Mar 2026
Site and admission
Apr 2026
Power MOU
Next
Construction